Waste Wood Shredding Line Upgrade with Zero Downtime

Azortum_Norsk-Gjenvinning_Wood Shredding Line_1200x628

How Norsk Gjenvinning increased throughput, achieved ISO P63 chip quality, and installed a new shredding line in just three weeks — without interrupting production.

1
Trusted by Norsk Gjenvinning, the Nordic region's leading environmental services provider
2
Designed, engineered and installed by Azortum
3
Project location: Oslo, Norway
4
Capacity: up to 35 t/h | 90,0000 t/year

When Capacity, Quality, and Continuity All Matter

Norsk Gjenvinning processes over two million tonnes of waste annually and plays a key role in supplying secondary raw materials for energy production and manufacturing.

Their existing waste wood shredding line could no longer keep pace with demand — but replacing it was not a straightforward equipment swap.

Key challenges included:

  • Inconsistent output quality due to oversized fractions and excessive fines

  • Requirement to meet ISO P63 chip size standards batch after batch

  • Installation inside a fully operational facility, directly next to the old line

  • Zero tolerance for extended downtime or production losses

The task was not just to increase capacity, but to stabilise output quality and protect downstream value.